Job work and subcontracting in ERPNext: stock at job workers, process costing and GST compliance
Ask a Tiruppur knitwear exporter how much yarn is sitting at the knitter today, how much grey fabric is at the dyer, and how much dyed fabric is waiting at the printer. Most will call three supervisors and still end up guessing. Then October comes, ITC-04 is due, and accounts rebuilds six months of challans from a register. Done properly, job work in ERPNext removes both problems: every kilogram that leaves your gate is tracked to a named job worker, every return is matched to the original challan, and the GST return comes out of the same records.

Why job work breaks most accounting-led systems
Job work is a stock problem first and a tax problem second. Your material is elsewhere, changes form there, and comes back in parts over weeks.
In Tiruppur the chain is yarn to knitting, grey fabric to dyeing, then printing or embroidery, often at three different units. In Coimbatore, a pump or valve maker sends castings out for machining, then plating or heat treatment. Each leg needs a challan, each return needs matching, and GST law puts a clock on all of it. That is the case for running job work in ERPNext rather than in a register.
How job work in ERPNext is modelled
ERPNext handles outward job work through its Subcontracting module. The building blocks are simple once you see them together:
- A non-stock service item for the job charge, and separate stock items for the material before and after the process.
- A Bill of Materials for the processed item listing what you supply, with “Supply Raw Materials for Purchase” ticked on that item.
- A warehouse for each job worker, so material at their premises still shows in your stock.
- A Purchase Order marked Is Subcontracted, at the agreed service rate, from which you create a Subcontracting Order.
- A Stock Entry with purpose Send to Subcontractor, made from the Subcontracting Order.
- A Subcontracting Receipt when processed goods come back, consuming supplied material from the job worker’s warehouse.
The Subcontracting Receipt behaves like a backflush. On submit, it posts the stock ledger and accounting entries, valuing the processed item at the cost of supplied material plus the service charge. The Purchase Receipt made later from the Purchase Order does not move stock again. Frappe’s subcontracting documentation walks through each screen.
One setting needs a deliberate decision. ERPNext can backflush raw materials on the BOM or on what was actually transferred. BOM-based consumption is simpler but will consume material you never sent. For job work in ERPNext with real variation, we usually prefer the transferred basis, and let stores correct the Consumed Quantity on the receipt.
Process-wise stock at every job worker
The warehouse-per-job-worker design answers the “how much is where” question. Stock Balance filtered on job worker warehouses shows quantity and value at each unit, and the standard subcontracting reports show what is still to be sent and received against open orders.
For a knitwear unit, each stage becomes its own item: yarn, grey fabric, dyed fabric, printed fabric. Knitting is one Subcontracting Order that turns yarn into grey fabric. Dyeing is a second order that takes grey fabric as its supplied material. The stock report then tells you how many kilograms sit at the dyer as grey fabric, not just “fabric somewhere”.
Rule 45 of the CGST Rules allows goods to move directly from one job worker to another, and many Tiruppur units send fabric straight from knitter to dyer. The documents should still record both legs so that stock and ITC-04 show the movement. Settle this in the first design workshop, not after go-live. Our ERPNext for textile manufacturing page covers the wider set-up.
Process loss and costing per process
Every process loses something. Knitting produces waste, dyeing changes weight, machining leaves swarf. Ignore it and the job worker’s warehouse fills with phantom stock nobody can find.
Handle it in three places. Build expected loss into the BOM quantity so standard consumption is realistic. Add scrap items where the waste has value; the Subcontracting Receipt picks them up at valuation rate or BOM scrap rate. Then correct actual consumption on each receipt when the yield differs. Over a season, standard versus actual loss by job worker is one of the most useful numbers a plant head can have.
Costing follows. Each Subcontracting Receipt adds the service charge to the supplied material, so dyed fabric carries yarn cost, knitting charge and dyeing charge, stage by stage. That is the cost per process that usually lives in an Excel sheet. Our note on ERP for garment exporters shows how it feeds style-wise costing.
Engineering works the same way. A Coimbatore pump maker can track an impeller as a raw casting, a machined casting and a coated part, with charges added at each stage. See ERPNext for pump manufacturing for how job work in ERPNext sits alongside in-house Work Orders.
GST rules for job work in ERPNext
Section 143 of the CGST Act lets a registered principal send inputs and capital goods to a job worker without paying tax, under a challan. The goods must come back, or be supplied onward, within set periods.
| Rule | What the law says | What to track in ERPNext |
|---|---|---|
| Inputs sent for job work | Return within one year of being sent out, or it is treated as a supply by the principal on the date sent | Age of open Send to Subcontractor entries per job worker |
| Capital goods sent for job work | Return within three years, otherwise treated as supplied | Asset or stock entries to job workers, with dates |
| Moulds, dies, jigs, fixtures, tools | Excluded from these time limits | Keep them on separate challans so ageing is not distorted |
| Waste and scrap at job worker | Can be supplied directly by the job worker, with tax paid by them if registered | Scrap items on the receipt, and a clear agreement on who sells it |
| Inter-state movement to job worker | The principal must generate the e-way bill, irrespective of consignment value | e-Waybill on the Send to Subcontractor Stock Entry |
| ITC-04 return | Half-yearly if aggregate turnover in the previous year was above ₹5 crore, annual otherwise | Challan-level data for goods sent, received back and moved between job workers |
The ITC-04 change came through Notification 35/2021-Central Tax, effective 1 October 2021. Half-yearly filers report April to September by 25 October and October to March by 25 April. Annual filers report the full year by 25 April. With the April to September period just closed, this is a good month to test whether your records of job work in ERPNext can produce this return. Confirm the treatment of your specific case with your chartered accountant.
What India Compliance adds
The India Compliance app fills the GST side of job work in ERPNext. With e-Waybill generation for subcontracting switched on in GST Settings, you can generate an e-way bill from a Send to Subcontractor Stock Entry, treated as a Delivery Challan. The Subcontracting Receipt is also supported. Entries carry document references back to the original challan, which is what ITC-04 needs.
For the return, the GST Job Work Stock Movement Report lists goods sent for job work and received back, and exports JSON for upload to the GST portal. If you also do job work for customers, recent releases added e-way bill support for subcontracting inward. For the broader GST set-up, see GST e-invoicing in ERPNext.
Who should own what
Job work fails when everyone assumes someone else is matching challans.
| Role | Owns | Checks every week |
|---|---|---|
| Purchase or job work coordinator | Subcontracting Orders, rates, job worker master data | Open orders with nothing received |
| Stores | Send to Subcontractor entries, Subcontracting Receipts, consumed quantity | Stock at each job worker warehouse against their own count |
| Production or plant head | BOMs, expected loss, scrap items | Actual versus standard yield by job worker |
| Accounts | Service charge invoices, e-way bills, ITC-04 | Inputs approaching the one-year limit |
Setting up job work in ERPNext: a practical sequence
- List every process you send out and every job worker, with GSTIN and state.
- Decide the item for each stage (yarn, grey, dyed, printed; casting, machined, coated) and create service items for each charge.
- Create one warehouse per job worker, grouped under a parent “At job workers” warehouse.
- Build BOMs with realistic consumption, and add scrap items where waste has value.
- Choose the backflush basis and test it on two or three real orders.
- Enable e-Waybill for subcontracting in GST Settings and test an inter-state challan.
- Migrate open material at job workers as opening stock in their warehouses, with the original challan dates noted for the time limits.
- Run the GST Job Work Stock Movement Report for a past period and compare it with your last ITC-04.
Step seven is where we see projects slip. If opening stock at job workers is loaded without the original send-out dates, one-year tracking for job work in ERPNext starts on go-live day and gives false comfort.
Sending material out every day? We set up job work in ERPNext for knitwear, engineering and pump units across Tamil Nadu, from BOMs to ITC-04. Book a free 30-minute ERPNext consultation and bring your current challan register.
Frequently asked questions
Does ERPNext support job work and subcontracting?
Yes. Job work in ERPNext runs through the Subcontracting module: a subcontracted Purchase Order, a Subcontracting Order, a Send to Subcontractor Stock Entry for material going out, and a Subcontracting Receipt for processed goods coming back.
Can ERPNext generate an e-way bill for a job work challan?
With the India Compliance app, yes. After enabling e-Waybill generation for subcontracting in GST Settings, you can generate it from the Send to Subcontractor Stock Entry, which is treated as a Delivery Challan.
How do I file ITC-04 from ERPNext?
India Compliance provides the GST Job Work Stock Movement Report, which lists goods sent and received back and exports JSON for the GST portal. Check it against your challans before filing.
How often is ITC-04 filed?
Since October 2021, half-yearly for principals whose aggregate turnover in the previous financial year exceeded ₹5 crore, due 25 October and 25 April, and annually for others, due 25 April.
What happens if job work material is not returned within a year?
Under Section 143, inputs not returned or supplied within one year, and capital goods not returned within three years, are treated as supplied by the principal to the job worker on the date they were sent, and tax becomes payable.
How is process loss handled in ERPNext subcontracting?
Build expected loss into BOM quantities, add valuable waste as scrap items, and correct the consumed quantity on the Subcontracting Receipt when actual usage differs.
Job work in ERPNext: key takeaways
Job work in ERPNext uses Subcontracting Orders, Send to Subcontractor Stock Entries and Subcontracting Receipts, with a warehouse for each job worker so you always know what material is where and in what form. Model each process stage as its own item, put expected loss and scrap in the BOM, and the receipt will build cost per process automatically. On the GST side, track the one-year and three-year limits under Section 143, generate e-way bills from the challan entry, and file ITC-04 half-yearly or annually depending on turnover. The India Compliance guide to the subcontracting workflow for Indian compliance is a useful read for your accounts team.